NEWSLETTERS
 
The Consensus
Principle
(Commended,
SCL Hudson
Prize 2002)
 
THE LAWBUILD LETTERS
 
 
 
 
 

LAWBUILD Newsletter No. 3

July 2002

 

Lawbuild provides construction law expertise
to save clients time and money.

A personal message from Lawbuild's Principal
David Lewis

Dear Reader

I hope that you will find some of the articles and features in Lawbuild Newsletter No. 3 not only useful, and relevant to your business or profession, but also an interesting and enjoyable read.

With kind regards.

Principal
Lawbuild, solicitors

Contents

News and views
Tips and tricks
Lawbuild offers free legal services!
A glossary of construction law expressions: C is for ...
Introducing our featured article
Warranty or not warranty?  VAT is the question
This and that
Business Network International
About Lawbuild
About you
Lawbuild's new website up and running
Legal disclaimers and warnings relating to this Newsletter: please read
How to contact Lawbuild (or unsubscribe)

News and views

Return to contents

Fire damage: designers liable but contractor and subbie walk away

In 1993 Co-operative Retail Services (CRS) engaged Wimpey as main contractor to build a large new office block.  Hall was the electrical subcontractor.  Taylor Young Partnership were the architects, and Hoare Lea & Partners were the consulting engineers.

CRS, Wimpey and Hall were jointly insured against fire damage to the works.

Before practical completion a fire extensively damaged the new building.  The insurers duly paid up; then they looked around to see who might have been responsible, through negligence, for the fire.

Had Wimpey or Hall been negligent?  Maybe (it hadn't been proved), but the insurers couldn't sue them because Wimpey and Hall were their insured.  However, because the insurers had met the claim they could and did make CRS sue the two consultants.

The consultants said: "It wasn't our fault, or at least it wasn't only our fault: Wimpey and Hall were negligent, and if we have to pay the insurers' losses then Wimpey and Hall must pay us a contribution representing their fair share of those losses."

To win that argument legally, the consultants had to prove that Wimpey and Hall were liable to CRS for the fire damage.  And if Wimpey and Hall weren't liable to CRS, then they weren't liable to the consultants.

It is usually cheaper and quicker for the courts to sort out legal issues before factual ones.  So the judges assumed, purely for the purposes of legal argument, that various negligent breaches of contract by Wimpey, Hall and the two consultants were what caused the fire.  But in fairness to all concerned we should point out that no-one had yet been proved negligent.

So (assuming negligence by the consultants, the main contractor and the electrical subcontractor) were Wimpey and Hall liable to CRS?  The building contract was the predecessor to today's JCT 98 Private With Quantities, and the relevant clauses (20 and 22A) have not changed materially since then.  When you read them for the first time they seem to exclude the contractor's liability for damage to the works.  When you read them a second time, especially with a legal eye, you're not quite so sure.

This issue ended up in the House of Lords, Britain's highest judicial authority, which gave judgment at the end of April.

Lord Hope of Craighead said that in his opinion the main contract did exclude Wimpey's liability to CRS for loss and damage which was caused by the fire and due to Wimpey's breach of contract.  The same reasoning applied to Hall, the electrical subcontractor.  So, since CRS were not entitled to recover compensation from Wimpey and Hall for the fire damage, the two consultants could not recover a contribution from Wimpey or Hall.

This conclusion could lead to a very unfair result, as the consultants' counsel had pointed out: a party with a very minor responsibility for causing a catastrophe might end up bearing the entire financial consequences.  Lord Bingham of Cornhill noted:

"This is indeed a possible outcome, and may be the case here.  But this is the effect of the standard form contract which CRS, Wimpey and Hall made, and it is a standard form of which [the two consultants] and their professional indemnity insurers must be taken to have been aware.  It would no doubt have been open to [the consultants] to seek to be included as co-insured in the joint names insurance, or to have made other arrangements.  In reality, the present issue arises between [the consultants'] indemnity insurers on one side and the joint names insurers on the other.  The latter have provided the full indemnity they undertook to give.  The real complaint of the former is the failure to take steps to guard against the contingency which has in fact occurred, a contingency which could in my opinion have been foreseen had the right questions been asked at the right time."

So what can design consultants and/or their insurers do to avoid carrying the can for the main contractor's or a subcontractor's negligence?

Logically, any industry-wide solution would have to either absolve designers from liability or impose liability on main contractors and subcontractors.  The first option would need the agreement of the insurance companies who cover damage to the works, and the second would need the consent of contractors and subcontractors.  In our view, none of these powerful interests can realistically be expected to make such concessions to designers, and the likely long-term consequence is yet more increases in consultants' insurance premiums.

For a fuller report on Co-operative Retail Services v. Taylor Young Partnership & Hoare Lea & Partners, House of Lords, 25 April 2001, click here.

Tips and tricks

Return to contents

There's a snag in this contract

JCT contracts require the architect or contract administrator named in the contract, or - under JCT 98 With Contractor's Design - the employer (usually acting through the employer's agent), to certify practical completion (PC) when the contractor has completed the works in accordance with the contract.  In theory the certifying consultant may be entitled to withhold the PC certificate if there are any defects or incomplete work, though judicial statements indicate that construction work is not like the manufacture of goods and that absolute perfection cannot be expected.

Be that as it may, in practice there is often economic, commercial or political pressure by the employer on the consultant to certify PC notwithstanding a degree (sometimes quite a large degree) of defective or incomplete work.  For instance, the employer may suffer a financial disadvantage if a retail tenant is unable to occupy the completed property before the Christmas shopping period, and neither he nor the tenant will want to delay the handover on account of a handful of minor defects.

How can the consultant protect himself vis-à-vis the employer, and the employer vis-à-vis the contractor, if he certifies PC despite defects or incomplete work?

First, he should obviously make sure that the employer has authorised him to issue a PC certificate in those circumstances, i.e. where the building contract does not oblige him to do so, and that no question can arise in the future as to whether or not this authorisation was given.

Secondly, he should make sure that the contractor will be contractually obliged to complete any outstanding work and make good the defects.

But (we hear you say), surely all the consultant has to do is include the defects and incomplete work in a snagging list and attach it to the PC certificate.  Right?

Wrong!  Because these particular "snags" are not ones that appear after PC but are known to exist at PC.

This makes a difference, because under some JCT contracts the post-PC contractual procedure for making good defects only applies to defects appearing after PC.

For example, JCT 98 Private With Quantities, clause 17.2: "Any defects, shrinkages or other faults which shall appear within the Defects Liability Period . shall be specified by the Architect . and . shall be made good by the Contractor .".

Remember, the defects liability period (DLP) begins at PC, so "within" the DLP must mean after PC.

And MW 98 talks about defects which appear "within three months" of PC.  Again, this seems to mean after PC (though it could be read differently).

On the other hand, IFC 98 refers to defects etc. "which appear . not later than 14 days after the expiry of the defects liability period".  Logically that could include defects appearing before PC.

The best practice when using JCT contracts, is to prepare a snagging list and require the contractor to sign an undertaking, before the PC certificate is issued, to complete or make good the items listed.

If you don't do this, you may find that the contractor is not legally obliged to make good the defects which existed at completion, or to complete the outstanding work, even though you have attached a snagging list to the PC certificate.  He could simply say, "I'm only required to make good defects which appear within the DLP.  These defects existed before the DLP began, so I'm not required to remedy them."

The contractor may nonetheless be liable to pay damages to the employer for the cost of remedying those defects or completing the outstanding work because the contractor is still in breach of contract: in fact the snagging list is evidence that the employer hasn't waived his right to sue.  But a duty to pay damages is not the same as a duty to actually go back to the site and make good the defects etc.

The contractor's undertaking should be along these lines:

To the Employer

Dear Sirs

Lawbuild House, London N3

In consideration of your authorising the [Architect] [Contract Administrator] [Employer's Agent] to issue a [certificate] [statement] of practical completion [for Section 00] notwithstanding the defects and incomplete work in the attached snagging list, we will make good such defects and complete such work at no cost to you by not later than [date].

Yours etc.

[Signed by Contractor]

Once the employer has that signed undertaking, the consultant can issue the PC certificate (with or without the snagging list attached to it) in the knowledge that the contractor will be under a contractual obligation to deal with those snags.

Lawbuild offers free legal services!

Return to contents

Subject to conditions (see below), Lawbuild is offering 1h 30m of free legal services to readers of our Newsletter whose organisations are either property developers, local authorities, charities, construction companies, or specialist contractors.

If that description fits you, then to benefit from this offer please email questionnaire@lawbuild.co.uk by not later than Friday 12 July 2002.  During the following week we will email you a market research questionnaire for you to complete and email back to us by Wednesday 31 July 2002.  Your replies will be treated in strict confidence.

After returning the completed questionnaire to us by 31 July, you can instruct us at any time between 1 August 2002 and 31 December 2002 to provide up to 1h 30m of whatever legal advice, drafting, negotiation or other legal services you or your company may need.

This offer is subject to the following conditions:

  • If any travelling is necessarily involved we may at our discretion extend the free time by up to one hour to include all or some of the travelling.

  • We cannot accept instructions involving work outside our specialist fields of (a) development-related (i.e. non-contentious) construction law and (b) contracts for services and other non-specialist agreements.  At our discretion we may agree to advise on a dispute where adjudication, arbitration or litigation are not immediately threatened or under way.

  • Solicitors' normal regulatory and professional duties apply.  For instance, we can't accept instructions where there might be a conflict of interest.

  • While we will endeavour to provide the free services as soon as possible after receiving your instructions, the offer does not apply to any instructions which have a deadline or are otherwise urgent.

  • If the work involved is likely to exceed the free period, we will tell you our charges for the extra work and obtain your agreement before doing it.

  • In the somewhat unlikely event that we are swamped with completed questionnaires, we reserve the right to change the period during which you may give instructions, which we will do by notifying you of the new period (which might be, for example, from 1 January 2003 to 30 June 2003).

A glossary of construction law expressions: C is for ...

Return to contents

CDM

The Construction (Design and Management) Regulations 1994.  Health and safety regulations requiring clients to appoint a planning supervisor and a principal contractor, and providing for a health and safety plan and a health and safety file.

Client

The person commissioning the works, who is called the client in appointments, the employer in building contracts, and the developer in development agreements and funding agreements.

Collateral warranty

The theoretical reasons for collateral warranties are twofold: (1) the common law doctrine of privity of contract, which prevents a person from suing under a contract to which he is not a party; and (2) rulings of the House of Lords in 1989 and 1990, which prevent the recovery of "economic loss" (i.e. the cost of remedial work) in an action in tort for negligent design or construction.

The collateral warranty is one of the most important documents in construction.  Its main purpose is to provide security for a fund, tenant or buyer ("third party").  It's an agreement under which a consultant, contractor or subcontractor warrants to a third party (essentially) that it has complied (and/or will comply) with its appointment, building contract or subcontract.

It is important that the benefit of the warranty should be freely assignable, usually twice.  Unless it can be assigned to a buyer the warranty is valueless to him, so assignability makes the property more marketable.

If a third party can't take an assignable warranty, it may be reluctant to lend money to the developer, or to buy or take a lease of the property.

The Contracts (Rights of Third Parties) Act 1999 has modified the doctrine of privity of contract, but has so far had little or no impact on collateral warranties.  (We did once believe that the Act would eventually be used to replace warranties from subcontractors and trade contractors, but that time now seems to be some way off.)

In 1997 the Construction Law Journal published an article by our Principal, David Lewis, about the JCT standard forms of agreement for collateral warranty, which contained a brief history of collateral warranties.

Judges sometimes consult articles in learned publications before arriving at their decisions.  In this way it is occasionally possible for the writer of such essays to influence the development of the common law or the interpretation of enactments.  And, as it happened, in 2000 Lord Goff of Chieveley and Lord Millett mentioned David Lewis's article in a leading House of Lords case on collateral warranties, Alfred McAlpine Construction Ltd v. Panatown Ltd.  Lord Goff said:

".I have been impressed by the suggestion of Mr. David Lewis . that the real purpose of the [duty of care deed, i.e. collateral warranty] was to provide a contractual remedy in negligence (comparable to that formerly available in tort under Anns v. London Merton Borough Council [1978] A.C. 728 before that case was departed from by your Lordships' House in Murphy v. Brentwood District Council [1991] 2 A.C. 398) against McAlpine by subsequent owners of the building."

Lord Millett said:

"I agree with the Court of Appeal that the [collateral warranty] was primarily designed to cater for subsequent purchasers. This is also the view expressed by Mr. Duncan Wallace Q.C. in "Third Party Damages: No Legal Black Hole?" (1999) 115 L.Q.R. 394 and is confirmed by an article by Mr. David Lewis in (1997) 13 Const. L.J. 305.  He notes that the widespread use of collateral warranties . derives from the change in the law of tort which occurred in 1990 when the House decided Murphy v. Brentwood District Council [1991] 1 A.C. 398 and departed from Anns v. Merton London Borough Council [1978] A.C. 728."

You can read our featured article on Alfred McAlpine Construction Ltd v. Panatown Ltd in this newsletter.

Construction Act

Part II of the Housing Grants, Construction and Regeneration Act 1996, which provides for adjudication and also regulates the payment provisions of appointments, building contracts and subcontracts.

Construction management

A procurement system which cuts out the main contractor.  The employer enters into trade contracts direct with companies who would normally be subcontractors but who are called trade contractors under construction management.

Often the employer will appoint a construction manager (who may be a contractor's subsidiary, but is more like a consultant than a contractor) to plan and manage the project, and to invite tenders for and negotiate, and then administer and supervise, the trade contracts.  But this function can also be undertaken by the employer in-house or by the quantity surveyor or another consultant with project management ability.

Consultant

A professional with technical qualifications.  Can be a designer (architect, structural engineer, mechanical and electrical services engineer).  Can also be a quantity surveyor, project manager, environmental consultant or planning supervisor.

Contract administrator

Under traditional contracting, a consultant, or an employee of the employer, whose job it is to issue instructions to the contractor, to certify payments under the building contract, to certify practical completion and completion of making good defects, and to issue the final certificate.

The contract administrator is often the architect.

The equivalent in design and build is the Employer's Agent (who is likely to be a quantity surveyor or project manager).

Contract sum

The consideration which the employer pays the contractor for the works, and for the completion of any design.

The contract sum is usually stated in the articles of agreement in the building contract.  However, it can be changed up or down by variations, ascertained direct loss and/or damage, liquidated and ascertained damages, and other contractually permitted adjustments.

Prime cost forms of contract (such as the management contract) do not state the contract sum in the articles of agreement because it cannot be ascertained when the building contract is signed.

The contract sum is usually payable by monthly instalments.  Under traditional contracting the quantity surveyor produces a (usually monthly) "valuation" of the work properly executed to date.  By "valuing" the work the quantity surveyor is calculating the proportion of the contract sum which is attributable to the work done.  The contract administrator then issues a (monthly) interim certificate stating the appropriate payment to the contractor, which is the quantity surveyor's valuation less (a) sums previously certified and (b) retention.

Contract Sum Analysis

In design and build, a breakdown of the contract sum.  Its main purpose is to enable the Employer's Agent to value Changes in the Employer's Requirements (or variations).  Usually found at the end of the Contractor's Proposals.

Contractor's Proposals

A document prepared by the contractor under design and build procurement, showing how the contractor proposes to meet the Employer's Requirements.

Contracts (Rights of Third Parties) Act 1999

This enactment came fully into force in May 2000.

It enables someone who is not a party to a contract - a third party - to sue either party to the contract where the contract expressly gives him the right to enforce a particular provision or the provision shows an intention to benefit him.  The Act also allows a third party to use any defence which the contract makes available to him, e.g. to an action by either party in tort.

The parties can agree in the contract to exclude the Act, and many if not most construction agreements do this.

The Act was originally seen as an instrument for replacing collateral warranties, but warranties continue to flourish.

Introducing our featured article

Return to contents

A timeless theme running through construction case law is the problem of the contracting party with no legal interest in the subject-matter of the contract.

The House of Lords delivered judgment on one of these cases on 27 July 2000.  This briefer than usual article summarises the current state of the law, and offers some general views on the dangers of focusing too hard on tax avoidance alone.

Now read on (and please excuse the atrocious pun in the title) .

Warranty or not warranty?  VAT is the question

Return to contents

Alfred McAlpine Construction Ltd v. Panatown Ltd arose out of the development of an office building in Cambridge belonging to Unex Investment Properties Ltd (UIPL).

You would have expected UIPL to have entered into the building contract with the contractor, McAlpine.  But that's not what happened.  As you know, many transactions are tax-driven, and in this case there was a big VAT saving to be made if the contractor was engaged not by UIPL but by its sister company, Panatown, both companies being members of the Unex Group.

Panatown later sued McAlpine, for defective work and delay.

The House of Lords did not let Panatown recover substantial damages from McAlpine in its own right, because Panatown had no duty to account to UIPL, and because it had no intention of using the damages to effect remedial works.

They also refused to let Panatown recover the cost of remedial works on behalf of UIPL, because McAlpine had given a collateral warranty to UIPL, thereby enabling it to sue the contractor direct.

But couldn't UIPL have sued McAlpine under the warranty?  Yes, but the warranty was not legally strong enough.  And therein lies one key lesson of this case, which demonstrates the need for a party at risk to have direct and adequate security.

A further point occurs to us.  We don't know exactly how much VAT was saved by making Panatown enter into the building contract instead of UIPL, but from internal evidence we would guess that it was around £1.3 million.  And according to Lord Goff of Chieveley, "The defects in the building alleged by Panatown are very serious; indeed it appears that the building may have to be demolished and rebuilt. The total damages claimed by Panatown run to many millions of pounds."

So it seems that the Unex Group tried to save themselves around £1.3 million by structuring this development in a way which ended up costing them "many millions of pounds".

If this analysis is correct, does it suggest that tax-saving devices should be shunned?  Not at all.  It is however a strong argument for examining not only the tax implications but also other relevant considerations: in this case, the construction law consequences.

You can read the transcript of Alfred McAlpine Construction Ltd v. Panatown Ltd by clicking here.

This and that

Return to contents

Missed Lawbuild Newsletters Nos. 1 and 2?

Email backissues@lawbuild.co.uk to request either or both of our previous issues.

A case of mistaken identity

We recently sent a mailshot promoting Lawbuild to a number of companies.  Generally the response was polite and positive, except for a fax we received from a man who was under the impression that we were "the same Mr Lewis" who had acted for him in connection with a property in a town or village we had never heard of before.

He wrote that he was most unhappy with the manner in which he alleged we had handled this matter, and with "the grossly excessive charges."  Moreover, he did not understand how we could purport to be solicitors, when we did not have, as he recalled, "a recognised qualification."

He added a handwritten postscript, perhaps redundantly: "PS - I am not interested!"

We sent him a polite reply, explaining that we had never acted for him or his company, and pointing out that David Lewis had become a solicitor in 1969 and had held a practising certificate continuously since then.  We also promised to remove his name from our mailing list.

Incidentally, our correspondent (who has not favoured us with an apology since receiving our reply) is no junior member of staff but is the managing director of a public limited company.

We're not quite sure what the moral (or even the point) of this story is.  "Don't jump to conclusions", perhaps.

Business Network International®

Return to contents

Lawbuild and David Lewis are a member of the Victoria (London) Chapter of Business Network International (BNI).

BNI is a business and professional networking organisation whose purpose is to generate quality referred business for its members.  BNI can claim to be the most successful organisation of its kind in the world, as it records the business transacted on a weekly basis.  In 2001 the 50,000 members of BNI worldwide passed 2,100,000 referrals generating over £500 million of business.  Currently, there are more than 2,300 groups, of which 330 are in the UK and Ireland.

BNI groups limit membership to one person per business, so members have an opportunity to lock out their competition.

BNI insists on references before a member can be accepted, and requires members to sign up to a code of ethics.  These safeguards, together with testimonials from other members, promote confidence in the products and services offered by members.  So whether you need a financial adviser, a florist or a carpenter, before picking up the Yellow Pages it may be worth having a word with us.

You can also contact us to ask about the benefits of becoming a BNI member, and we can arrange for you to attend one or two meetings as a visitor and without obligation.

To learn more, visit the BNI website.

About Lawbuild

Return to contents

Lawbuild is a specialist construction law practice offering expert advice and services to anyone carrying out or lending money for construction, and to any buyer, seller, landlord or tenant of recently built or refurbished property.  We are experienced, thorough and professional.  Our aim is to save clients time and money, and our charges are very reasonable.

Lawbuild is equally at home with contracts for services and with many other kinds of non-specialist agreement.

Lawbuild's principal, David Lewis, has more than 25 years' experience in contracts and construction law.

About you

Return to contents

We are sending this newsletter to a number of people we know (and to some we don't) in the property and construction sectors and the legal profession, and to selected members of BNI (Business Network International).  Even if you don't instantly recall the names "Lawbuild" and "David Lewis" (though we hope you will), it may well be that you have met us before, and possibly in the past few months.

We hope you will find this newsletter of interest to you, but if you prefer not to receive future issues you may easily "unsubscribe" by emailing us to that effect.

In any event, please feel free to forward this newsletter to anyone else you think might like to receive it.  And we shall be glad to add that person to our mailing list for future newsletters (we plan to increase their frequency to six times a year) if you or they will send us their email address.

Lawbuild's new website up and running

Return to contents

On 23 May 2002 our new website went live on the Internet.  Designed by BNI member Karim Cortbawi of Betternet, the new site -

  • profiles Lawbuild

  • contains a flattering (yet accurate) photograph of our Principal, David Lewis

  • describes the clients who need Lawbuild and what we can do for them

  • summarises Lawbuild's charging practices

  • contains three of our recent articles on important legal topics

  • quotes from various testimonials we have received

  • provides links to BNI offices and some fellow members of the Victoria chapter

Visit us at www.lawbuild.co.uk.

Legal disclaimers and warnings relating to this Newsletter: please read

Return to contents

Disclaimers

Lawbuild is providing this newsletter on an "as is" basis and makes no representations or warranties of any kind with respect to this newsletter or its contents and disclaims all such representations and warranties.

In addition, Lawbuild makes no representations or warranties about the accuracy, completeness, or suitability for any purpose of the information published in this newsletter.  The information contained in this newsletter may contain technical inaccuracies or typographical errors.  All liability of Lawbuild howsoever arising for any such inaccuracies or errors is expressly excluded to the fullest extent permitted by law.

Neither Lawbuild nor any of its employees or other representatives will be liable for loss or damage arising out of or in connection with the use of this newsletter.  This is a comprehensive limitation of liability that applies to all damages of any kind, including (without limitation) compensatory, direct, indirect or consequential damages, loss of data, income or profit, loss of or damage to property and claims of third parties.

Notwithstanding the foregoing, none of the preceding exclusions and limitations is intended to limit any rights you may have as a consumer under local law or other statutory rights which may not be excluded or in any way to exclude or limit Lawbuild's liability to you for death or personal injury resulting from our negligence or that of our employees or agents.

Intellectual property

The Lawbuild trade mark has been registered under the Trade Marks Act 1994 in respect of Classes 16 and 42, and application is pending in respect of Class 41.  All other trade marks, brand names, product names and titles and copyrights used in this newsletter are trade marks, brand names, product names or copyrights of their respective holders.  No permission is given by Lawbuild in respect of the use of any of them and such use may constitute an infringement of the holder's rights.

How to contact Lawbuild (or unsubscribe)

Return to contents

To remove your name from the mailing list for this newsletter, please email unsubscribe@lawbuild.co.uk (or request removal in a reply to the email enclosing this newsletter).

To add your name to our mailing list, please email subscribe@lawbuild.co.uk

All feedback is very welcome.  We would like to hear from you if you have any comments, queries, corrections or suggestions!

Here's how to get in touch with us:

Email

newsletter@lawbuild.co.uk (better than replying to the email enclosing this newsletter because when we print your reply we'd rather not end up printing the entire newsletter!)

Phone

020 8346 6424

Fax

020 8346 0745

Mobile

078 8775 7606

Post

David Lewis
Lawbuild, solicitors
37 The Grove
LONDON
N3 1QT

Website

www.lawbuild.co.uk

Finally, we hope you've enjoyed reading Lawbuild Newsletter No. 3, and we look forward to hearing from you at any time.

Return to contents